Public Document Library Table of Contents
Number / Title / Dates / Link |
Summary |
|
Title: Revised Plans for Phase 2 Date: April 2004 Author: Seattle Parks Department Number of pages: 7 Link: Apr2004_RevisedPhase2Plans.pdf (239 KB) |
Acquired through a Public Disclosure Request, these drawings and construction costs outline three options2A, 2B, and 2Cfor a revised (downscaled) version of Phase 2 of the five phase project. The original plan for Phase 2 (as outlined in the Environmental Impact Statement, and summarized in Construction Phases and Costs), calls for four fields: one full size baseball field, one little league baseball field, one soccer field, and one rugby field. All of the revised Phase 2 options include one full size baseball field, one little league baseball field, and one soccer field. However, only two out of the three options (2A and 2C) include a rugby field and only option 2B includes the partial demolition of the Commissary building. After adding in industry standard "mark-ups" (i.e., contractor overhead and profit, administrative overhead, design contingencies to cover unseen and unquantifiable items, etc.) the estimated costs for all three revised Phase 2 options exceeds available funds by approximately $500,000 to $1,000,000. Adding in the full costs of a scaled down version of Phase 1 presented by the Parks Department at the April 21, 2004 Seattle City Council Parks Committee meeting, the total cost of a revised Phase 1 and Phase 2 exceeds available funds by at least $4,000,000. Phase 2A:
Phase 2B
Phase 2C
|
|
Title: Schematic Design Cost Estimate Rephrased, Prepared for the Berger Partnership Date: September 10, 2003 Author: C3 Management Group, on behalf of Berger Partnership Number of pages: Link: Sep03_CostEstimate.pdf (895 KB) |
This is an updated version of the Feb. 26 2002 cost estimate. Two interesting observations. First, the new cost estimate appears to shove a good chunk of phase 2 out to phase 3. And second, the cost estimate has gone up 10%+. Note that there appears to be pages missing (it is missing a page that matches the last page of Feb02_CostEstimate_A.pdf below). |
|
Title: Schematic Design Cost Estimate, Prepared for the Berger Partnership Date: February 26, 2002 Author: C3 Management Group, on behalf of Berger Partnership Number of pages: 40 Links: |
This cost estimate for the Magnuson Park Sports Fields project is based on the plan as outlined in the Environmental Impact Statement. The project is divided into five phases, as outlined in Construction Phases and Costs brief. The cost for each of the five phases is outlined on the last page of Feb02_CostEstimate_A.pdf document. The total project cost is estimated at $59.3 million. However, this figure does not appear to include the demolition of the Commissary Building, which is estimated to cost approximately $2 million. |
[Page last updated 4/26/04]